Project Name: Swan Pond Road Deck Pour
Check out some sights (video above) from our recent deck pour at the Swan Pond Road Bridge! This deck took around 830 Cubic Yards of concrete and was poured in two phases. We poured these starting at 3 AM to avoid traffic and hotter daytime temperatures! Huge thanks to Concrete Pump Partners and IMI for helping make everything run smoothly!
Links to our Partners on this Project:
Project Name: Machine Control
HBC has added several GPS enabled excavators into our equipment fleet. Project managers are able to create surfaces and linework in the office and upload it to these machines for our operators to work from in the field. Operators can view these excavations in a variety of 2-D and 3-D viewports that help us to be more accurate and efficient in our excavations.
Project Name: 191 Beams Setting
Take a look at Haydon Bridge setting Beams on the first bridge on the Wolfe County Section of the Mountain Parkway. Our Crews did an excellent job handling the beams and coordinating traffic to complete the task safely!
Project Name: Wolfe County
Prior to any work taking place on the bridge deck/superstructure, we always make sure proper horizontal lifelines are installed so our crews can work safely! Pictured here is the new bridge on the eastbound Mountain Parkway over KY-191 in Wolfe County.
Project Name: Richwood
See the picture above for the completed interchange of Richwood Rd and US 25 located in Walton, KY. Haydon Bridge Company constructed the retaining walls along with the Railroad bridge and three span bridge over Richwood Rd.